How to Read the S-Curve

By XER Reader Team • September 13, 2026 • 5 min read
How to Read the S-Curve

The S-Curve plots Planned Value, Earned Value and Actual Cost over time and gives the earned value figures at the data date. Pick it from the view button on the Views tab.

S-Curve view in XER Reader with the earned value figures at the data date above the chart, a dashed blue planned line rising to the whole budget, and the Earned Value and Actual Cost lines stopping at the data date marker
The figures at the data date above the chart, the planned line dashed in blue, Earned Value in green and Actual Cost in purple, both stopping at the data date.

The figures at the data date

FigureMeaning
Planned ValueThe part of the budget that should be done by the data date, going by the baseline
Earned ValueThe budget of the work that is done: each activity's budget times its percent complete
Actual CostWhat has been spent so far, or the labor units used so far
SVSchedule variance, Earned Value minus Planned Value
CVCost variance, Earned Value minus Actual Cost
SPIEarned Value divided by Planned Value. Under 1 is behind the baseline
CPIEarned Value divided by Actual Cost. Under 1 is costing more than budgeted
BACBudget at completion, the whole budget. Every percent in the view is a percent of it
EACEstimate at completion, Actual Cost plus what the schedule says is still to come
VACVariance at completion, BAC minus EAC

Planned Value, Earned Value and Actual Cost also show their share of the budget. Rest the pointer on any figure for its full name, the sum with this schedule's own numbers, and what the value says about the job.

A figure that does not apply is left out, not shown as zero. Planned Value, SV and SPI need a baseline to measure against. Earned Value and the figures built on it need at least one started activity. Actual Cost, CV, CPI, EAC and VAC are not shown when measuring in duration, which has no actual cost.

The line under the figures names the data date, what is being counted and the baseline measured against.

The toolbar

ButtonChoicesWhat it changes
PeriodDaily, Weekly (Mon - Sun), Weekly (Sun - Sat), Monthly, Quarterly, YearlyHow often a point is drawn. No figure changes
MeasureCost, Labor Units, DurationWhat everything is counted in. Until you pick, cost is used when the schedule carries cost, then labor units, then duration hours
Measure againstNone (current schedule), the four baselines, and the baselines saved in a Microsoft Project fileWhat the schedule is measured against
ValuesCumulative (running total), Per periodRunning totals, which give the S shape, or what each period adds on its own
LinesThe planned line, Earned Value, Actual CostWhich lines are drawn
ExportSaves the figures and a picture of the chart as an Excel file

The tick in Measure and Measure against sits on what is in use. A greyed entry is one this schedule cannot offer: a measure it does not carry, or a baseline slot marked (not assigned). Rest the pointer on an entry of Measure, Values or Lines to see what it does, or why it is greyed.

Measure and Measure against reach beyond this view. The Earned Value columns of the Activity table and the earned value section of the Schedule Analyzer report follow the same two choices. Each of those columns says in its definition what is in force.

What is measured against

ScheduleBaselines offered
Primavera P6The baselines assigned to the schedule, up to four. See How to Assign and Manage Baselines
Microsoft ProjectThe baselines saved inside the file, listed as MS Project Baseline and MS Project Baseline 1 to 10. The first one is used as soon as the file is open

With no baseline there is no Planned Value, SV or SPI. Pick None (current schedule), or open a schedule that has no baseline, and the dashed line becomes Planned (current schedule): the budget spread over the schedule's own dates as they stand now. It shows where the schedule is heading and is not a plan to be measured against.

Reading the chart

ElementMeaning
Dashed blue lineThe planned line: the budget spread evenly over each activity's baseline dates, up to the whole budget
Green lineEarned Value, up to the data date
Purple lineActual Cost, up to the data date
Vertical dotted lineThe data date
Labels under the chartEach point, with the month or year it belongs to beneath

Points before the data date are estimated. A schedule file records where each activity stands now, not where it stood in earlier months. The figures at the data date are exact. Before it, each activity's earned value and actual cost are spread evenly from its actual start to its actual finish, or to the data date while it is running.

Reading a period

Move the pointer across the chart. A vertical line follows the nearest point, a dot marks it on each line, and a card gives the period with the amount and percentage of each line. On the data date the card says Data date.

A Microsoft Project file with no status date

The data date is then taken from the latest progress the schedule records, and the line under the figures says it is estimated from the latest progress. A schedule in which nothing has started is read as of its planned start, and the line says so. One with no planned start either is read as of today.

When the chart is empty

MessageCause
No data, open a project to view the S-CurveNo schedule is open
There is nothing to draw yetNo activity has dates to draw a line from
No line is switched onEvery entry under Lines is off

On a very long schedule Daily gives way to a wider period, and the line under the figures says which one is drawn.

Requirements

Requires an open schedule and XER Reader Pro or XER Reader Cloud.

Home Pricing Downloads Articles Blog FAQ Contact