How to Read the Resource Usage Spreadsheet

How to Read the Resource Usage Spreadsheet

The right hand pane of the Resource Assignment view is a spreadsheet, not a chart. Every cell holds the units falling in one period, and the pane has its own selection, its own clipboard and its own navigation, all separate from the activity table beside it.

How the grid is built

Rows come from the activity tree on the left, and each activity contributes two of them. Columns come from the bottom row of the time scale. A cell is therefore one field of one assignment in one period.

Resource usage spreadsheet in XER Reader with the Fields column widened to show Budgeted/Planned Units and Remaining Early Units in full for every activity row
The Fields column names the two rows every activity gets. Widen it and the labels stop being cut off.
RowHolds
Budgeted/Planned UnitsThe units planned for the assignment in that period
Remaining Early UnitsThe units still to be done in that period

The two rows are why the activity rows in the left table are twice the usual height. Both panes scroll together vertically, and the row heights are kept in step so the two halves never drift apart.

The Fields column

The divider between the Fields column and the time scale drags, and the pointer changes to a horizontal resize arrow over it. The labels are elided to fit, so at the default width they read as Budgeted/Planned... and Remaining Early U...; widening the column shows them in full.

The drag is clamped at both ends. The Fields column cannot be narrowed past a minimum, and it cannot be widened past the point where the time scale would lose its own minimum width. Dragging to the far edge parks it at the limit rather than collapsing either side.

Reading a cell

A value is the units falling inside that period, to one decimal place, with the time unit abbreviation after it. A period with no units shows nothing at all.

Blank is not zero. Empty cells are left empty on purpose, so the periods that carry work stand out along the row. Do not read a blank run as a gap in the data; it is a gap in the allocation.

SettingWhere it comes from
The numberThe assignment, spread across the period the column covers
The unit and its abbreviationTools then Settings, under time unit
The period a column coversTimeline Settings, bottom row unit

Changing the bottom row unit from Day to Week or Month does not change the totals, only how they are gathered. The same assignment reads as five daily cells or one weekly cell.

Group bands carry no totals

A resource band shows no rolled up figure. The band rows are drawn with the grid and nothing else: no sum of the activities under them, in any period. To total a resource you have to read its activity rows, or take the numbers out to a spreadsheet. This is the one thing people expect from a usage view that this pane does not do.

Selecting cells

Click a cell to select it. That also selects the matching row in the activity table, so the two panes stay on the same activity.

Hold Shift and click a second cell to take the rectangle between the two. The block spans both field rows and as many periods as it covers, and it can run across several activities.

Resource usage spreadsheet in XER Reader with a block of cells selected across both field rows of one activity and three time periods, and the matching row highlighted in the activity table
A selected block: both field rows of one assignment across three periods, with the activity row highlighted on the left.
ActionResult
ClickSelects one cell and the activity row beside it
Shift and clickExtends the selection to a rectangle from the first cell
TabMoves the selection one cell right, wrapping to the start of the next row
Shift and TabMoves it one cell left, wrapping to the end of the previous row
EscapeClears the selection

Walking with Tab scrolls the pane to keep the selected cell in view, horizontally and vertically, so the selection cannot disappear off the edge. At the last cell of the last row it wraps back to the first.

The selection is dropped whenever the grid underneath it changes: a different number of rows, a reset model, or a change to the time scale that alters the number of columns. That is deliberate, because the cells the old rectangle pointed at are no longer the same cells.

Copying the numbers out

A selected block copies to the clipboard with the standard copy command. What lands is tab separated text, one line per field row and one column per period, which pastes into a spreadsheet with the periods across the top.

Copy on the ribbon is a different copy. It takes the selected rows of the activity table on the left, the columns of activity data. The units in the time scale only come out through the cell selection described here. If a paste arrives with activity names and no numbers, the ribbon button was used instead of the cell block.

The copy reads the values the same way the pane draws them, so what you paste matches what you saw, blanks included.

Jumping to where the work is

Double click a row in the time scale pane and it scrolls to the first period that has a value for that assignment. On a schedule running over years, with the columns set to days, that is the difference between finding an allocation and giving up on the scroll bar. Nothing on screen advertises it.

The jump animates rather than snapping, and it lands the first populated period a little in from the left edge so the run of work after it is visible. It looks at both field rows and goes to whichever starts earlier. An assignment with no units anywhere does not move the view.

Expanding and collapsing

Expansion belongs to the activity table on the left. The time scale pane deliberately does not respond to clicks on the expand arrows, because toggling a row in only one of the two panes would let them fall out of step.

The view opens with every band expanded.

Resizing the periods

The time scale header resizes by dragging, which widens or narrows the columns in place and is the quickest way to fit more periods on screen without opening a dialog. The same width is what Size in Timeline Settings sets, so a drag and the slider are two routes to one setting.

Requirements

Part of the Resource Assignment view, so it requires an open schedule with resource assignments and a signed in account.